People get raises, contractors renegotiate, and what an hour of someone’s time costs your business changes. Cost rates let you record what each resource costs per hour and the date each rate takes effect. Resource Hero then puts a cost on every hour you forecast and track, and totals it on each assignment and project.
Enter a Cost Rate
- From the Resources tab, open a resource.
- Select the Rates tab.
- In the Resource Rates related list, click New.
- Enter the Effective Date and Cost Rate, then click Save.

The resource’s rates are listed on the Rates tab, newest first.

How a Cost Rate Is Applied to a Forecast
Each Resource Forecast holds one resource’s forecast and actual hours for one date. When a Resource Forecast is saved, Resource Hero finds the resource’s rate with the latest Effective Date on or before the Forecast Date and applies it: the forecast’s Forecast Cost is that Cost Rate multiplied by its forecast hours, and its Actual Cost is the Cost Rate multiplied by its actual hours.
For example, a resource has two rates: $85.00 effective January 1, 2026, and $95.00 effective January 1, 2027. A forecast of 8 hours dated December 14, 2026 costs $680.00. The same 8 hours dated January 11, 2027 costs $760.00.
Change a Rate Over Time
When a resource’s cost changes, add another rate with the date the change takes effect. Leave the earlier rates in place: they keep the cost of earlier forecasts accurate.
- Open the resource and select the Rates tab.
- Click New, enter the Effective Date of the change and the Cost Rate, then click Save.
Resource Hero recalculates the cost of that resource’s forecasts dated on or after the Effective Date, including actual hours already tracked. Forecasts dated before it keep the earlier rate. The recalculation runs in the background, so totals can take a moment to update.
Each rate on a resource needs its own Effective Date. Saving a second rate with the same date displays “Effective dates must be unique for a given resource.”
When loading several years of rates for a resource at once, enter the most recent Effective Date first and work backward.
Where Costs Appear
Costs total up from each Resource Forecast to its Resource Assignment, and from there to the RH Project or Opportunity the assignment belongs to. The Data Model section below lists every cost field.
On an RH Project
The Summary tab shows the totals in the Costs section. The To Date tab compares the cost you forecast up to today with the actual cost so far. The All Time tab shows the forecast cost of the whole project.

The Budget / Timeline Health section, at the top of the same tab, compares Actual Cost with the project’s Budget.

The RH Project page also charts forecast and actual cost by month, and by resource and by role, to date or for the whole project.

Across Projects
The Project Financials Summary report lists every in-progress project by project manager, with Forecast Cost, Forecast Cost To Date and Actual Cost side by side. To run it, open the Resource Hero App Reports folder on the Reports tab.

The Financials by Related and Financials by Resource reports in the same folder break cost down by month. See Gain Insights with Reports and Dashboards.
On the RH Matrix
To see cost alongside hours on the RH Matrix, switch the matrix to its Forecast Cost or Actual Cost view. These views are read-only.
Before You Start
- Permission: creating, editing and deleting cost rates requires the Resource Hero – Rates Administrator permission set. See Resource Hero Permission Sets.
- Give each resource a rate dated on or before their first forecast. A forecast dated before a resource’s earliest Effective Date has a cost of zero.
- Cost follows the resource. An assignment with a role and no resource has a cost of zero until a resource is assigned.
- Multiple currencies: a rate is converted to the currency of each forecast it is applied to. See Multi-Currency Support.
- Validation rules: a validation rule on the Resource Forecast object must allow Resource Hero to update cost fields. See Validation Rules.
Data Model
To see how the objects on this page relate to each other, view Data Model: Cost Rates.
A Resource Rate belongs to one resource. Each Resource Forecast points to the Resource Rate that was applied to it, and its costs total up through the Resource Assignment to the RH Project.
Resource Rate Fields
| Field | API Name | Type | Description |
|---|---|---|---|
| Effective Date | Effective_Date__c | Date | The first day this rate applies. Required. The rate stays in effect until the resource’s next Effective Date. |
| Cost Rate | Cost_Rate__c | Currency | What one hour of this resource’s time costs your business. Required. |
| Resource | Resource__c | Master-Detail | The resource the rate belongs to. |
Cost Fields on the Resource Forecast
Resource Hero fills these in each time a Resource Forecast is saved.
| Field | API Name | Type | Description |
|---|---|---|---|
| Resource Rate | Resource_Rate__c | Lookup | The Resource Rate record that was applied. |
| Cost Rate | Cost_Rate__c | Currency | The hourly cost from that record. |
| Forecast Cost | Forecast_Cost__c | Currency | Cost Rate multiplied by the forecast hours. |
| Actual Cost | Actual_Cost__c | Currency | Cost Rate multiplied by the actual hours. |
| Billable Cost | RH_Billable_Cost__c | Formula (Currency) | Actual Cost when Is Billable is checked on the forecast. Otherwise zero. |
Cost Fields on the Resource Assignment
Each Resource Assignment totals the cost of its Resource Forecasts.
| Field | API Name | Type | Description |
|---|---|---|---|
| Forecast Cost | Forecast_Cost__c | Currency (Rollup) | The sum of Forecast Cost on the assignment’s Resource Forecasts. |
| Actual Cost | Actual_Cost__c | Currency (Rollup) | The sum of Actual Cost on the assignment’s Resource Forecasts. |
| Billable Cost | Billable_Cost__c | Currency (Rollup) | The sum of Billable Cost on the assignment’s Resource Forecasts. |
Cost Fields on the RH Project
Each RH Project totals the cost of its assignments, and compares it with the project’s Budget.
| Field | API Name | Type | Description |
|---|---|---|---|
| Forecast Cost | RH_Total_Forecast_Cost__c | Currency | The total forecast cost of the project’s assignments, for the whole project. |
| Forecast Cost To Date | Forecast_Cost_To_Date__c | Currency | The forecast cost of the project up to the current date. |
| Actual Cost | RH_Total_Actual_Cost__c | Currency | The total actual cost of the project’s assignments. |
| Billable Cost | RH_Total_Billable_Cost__c | Currency | The total billable cost of the project’s assignments. |
| Actual % of Forecast Cost | Actual_p_Forecast_Cost__c | Formula (Percent) | Actual Cost divided by Forecast Cost. |
| Actual % of Forecast Cost To Date | Actual_p_Forecast_Cost_To_Date__c | Formula (Percent) | Actual Cost divided by Forecast Cost To Date. |
| Blended Cost Rate | Blended_Cost_Rate__c | Formula (Currency) | The average actual cost per hour: Actual Cost divided by Actual Hours. |
| Planned Blended Cost Rate | Planned_Blended_Cost_Rate__c | Formula (Currency) | The average forecast cost per hour: Forecast Cost divided by Forecast Hours. |
| Budget Remaining | Budget_Remaining__c | Formula (Currency) | Budget minus Actual Cost. |
| % of Budget Used | p_Budget_Used__c | Formula (Percent) | Actual Cost divided by Budget. |
| Daily Burn Rate | Daily_Burn_Rate__c | Formula (Currency) | Actual Cost divided by the days elapsed on the project. |
Cost Fields on the Opportunity
Each Opportunity totals the cost of its assignments. See Resource Hero Rollup Fields to total costs on other objects.
| Field | API Name | Type | Description |
|---|---|---|---|
| RH Total Forecast Cost | RH_Total_Forecast_Cost__c | Currency | The total forecast cost of the opportunity’s assignments. |
| RH Total Actual Cost | RH_Total_Actual_Cost__c | Currency | The total actual cost of the opportunity’s assignments. |
| RH Roll-up Forecast Cost | RH_Roll_up_Forecast_Cost__c | Formula (Currency) | Displays RH Total Forecast Cost. |
| RH Roll-up Actual Cost | RH_Roll_up_Actual_Cost__c | Formula (Currency) | Displays RH Total Actual Cost. |