Most services teams watch one utilization number per person. It answers “how full was their month?” It does not answer the questions that decide revenue and staffing:

  • Was that 100% client work, or a week of vacation plus internal projects?
  • Is the person at 115% overloaded with billable work, or logging admin time on top of a normal load?
  • Is the team hitting its billable target, and if not, which months and which people fell short?

Because Resource Hero is built 100% native on the Salesforce platform, capacity, time off, holidays and project hours all sit in one place, so a standard Salesforce report can answer all three. This article shows what those answers look like, then how to build the two reports behind them.

See what filled each month

The first report shows three numbers for every resource, every month, all measured against the same full capacity:

  • Non-billable utilization: time off, holidays and non-billable project work.
  • Billable utilization: billable project hours.
  • Total utilization: the two added together. This is the number you already track.
The Utilization - Billable vs Non-Billable report by resource and month, May to September, with the Non-Billable %, Billable % and Total % columns for August highlighted.

The total is colored by overall workload for the month. The color says how loaded the person was and nothing more. It is the same whether the month was filled with client work, internal projects or time off.

  • Green, under 80%. The person had room to take on more.
  • Yellow, 80 to 100%. Fully booked.
  • Red, over 100%. More hours logged than the person had capacity for.

To see what filled a month, read the two percentages next to the total. Two red cells from the same June show the difference:

ResourceNon-Billable %Billable %Total %What happened
Charlotte Taylor20%105%125%Client work alone was more than a full month. This person needs work moved or help added.
Isabella Martinez31%78%109%Client work was under a full month. Internal work and time off pushed the total over.

Both are red, and they call for different responses.

Green covers everything under 80%, so a nearly empty month is green too. In a closed month that usually means missing time entries, not a quiet month, so scan the green cells for very low numbers before you invoice.

So this report answers “how busy is each person, and with what?” It does not grade anyone on billable work. That is the job of the second report.

A week off no longer looks like a slow month

Here is Henry Smith’s August before and after a week of approved time off:

Non-Billable %Billable %Total %
Before the time off14%61%76%
After the time off38%61%100%

The week off added 40 hours to a month with 168 hours of capacity, and all of it landed in the non-billable column. Billable utilization did not move. A month that looked like it had room to spare was a full one, and anyone reading the report can see why, with no side spreadsheet of who was out.

Each percentage is rounded on its own, which is why 38% and 61% show as a 100% total.

Henry Smith's August cells highlighted, showing 38% non-billable, 61% billable and 100% total.

Measure the team against a billable target

Workload and billable performance are different questions. Someone can be yellow or red on total utilization and still be well short of what you need them to bill. The second report drops everything except billable work and colors it against a target. In this example the organization’s target is 80% billable utilization per month, so the report shows green at 80% and above, yellow from 60 to 80%, and red below 60%.

The Utilization - Billable Only report with Capacity, Billable Hours and Billable % by resource and month.

There is a lot of red, and that is what the report is for. The Total row at the bottom tells the story for the whole team. It did not reach its 80% target in any month. June and July came close, at 71% and 74%. September fell to 31%, less than half the target. That is a conversation to have in the first week of October, not at quarter end. Either the pipeline thinned out or people are not logging their time, and the two need very different responses.

The same view works per person. Only 3 of the 32 people averaged 80% or better across the period. That tells you who is carrying the billable load and who has room to take on more.

One thing to decide before you set a target: this report measures billable hours against full capacity, and capacity does not shrink when someone takes time off. Henry’s August shows what that means. The Capacity column shows 168 hours for the month. The week off left 128 hours to work, so billing every one of them would still show 76%, not 100%. He billed 103 hours, which the report shows as 61%. Set targets with that in mind, or read this report next to the first one, where the time off is visible.

Build the reports

Both reports are built on a report type that ships with Resource Hero. Plan on about 15 minutes.

Prefer to skip the clicking?

Both reports are on GitHub at Resource-Hero/rh-solution-billable-utilization, ready to deploy with the Salesforce CLI.

Why it takes so little

Resource Hero stores every day’s hours on a Resource Forecast record with an Is Billable checkbox. Two fields on that record, Billable and Non-Billable, hold the hours for each case. Approved time off and holidays arrive as non-billable hours with no work on your part, and capacity sits in the same object. So the reports need a few short formulas and no new fields.

1. Start a new report

  1. Open the Reports tab and click New Report.
  2. Search for the Resources w/wo RH Data report type, select it, and click Start Report.
  3. On the Filters tab, set Show Me to All resources, then set the Created Date range to All Time. Click Apply on each.
  4. Add a filter on Forecast Date, click Use relative date, enter LAST 6 MONTHS, and click Apply.

A new report starts out limited to resources you own and to the current quarter. Step 3 opens it up to the whole team.

2. Group by resource and month

Weekly numbers are noisy and time entry is often only complete after month close, so this report groups by calendar month.

  1. On the Outline tab, under Group Rows, add Resource Name.
  2. Under Group Columns, add Forecast Date.
  3. In the report preview, click the dropdown next to Forecast Date, select Group Date By…, then Calendar Month.

Group on Forecast Date and not Week Beginning. A week that starts in one month and ends in the next would otherwise count entirely toward the month it started in.

The report builder Outline panel with Forecast Date as the column group and three summary formula columns.

3. Add the three columns

Click the dropdown next to Columns, select Add Summary Formula, and create the three columns below. Enter the name shown as the Column Name, set Formula Output Type to Percent and Decimal Points to 0, paste the formula, and click Apply.

Non-Billable %

MAX(0, IF(ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__Capacity__c:SUM > 0,
  ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__RH_Non_Billable__c:SUM /
  ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__Capacity__c:SUM, null))

Billable %

MAX(0, IF(ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__Capacity__c:SUM > 0,
  ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__RH_Billable__c:SUM /
  ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__Capacity__c:SUM, null))

Total %

MAX(0, IF(ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__Capacity__c:SUM > 0,
  ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__Actual__c:SUM /
  ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__Capacity__c:SUM, null))

Each formula divides hours by capacity and leaves the cell empty when a resource has no capacity that month.

The Edit Summary-Level Formula Column window showing the Billable % formula with a Percent output type.

At the bottom of the report builder, turn off Row Counts, Detail Rows and Stacked Summaries. The report then shows one line per resource.

4. Color the total

  1. Click Conditional Formatting at the bottom right of the report builder, then click Add Conditional Formatting Rule.
  2. Under Apply Conditional Formatting to, select Total %.
  3. End the first range at 80 and pick green. End the second range at 100 and pick yellow. Pick red for everything above.
  4. Click Done, then Apply, then Save & Run.
  5. Enter Utilization - Billable vs Non-Billable as the report name, select a folder your managers can see, and click Save.

5. Make the billable-only version

This report shows the hours behind the percentage, so it adds capacity and billable hours next to it.

  1. Click the dropdown next to Edit, select Save As, and save a copy of the report as Utilization - Billable Only.
  2. Click Edit, then Conditional Formatting. Delete the Total % rule and click Apply.
  3. Under Columns, remove Non-Billable % and Total %.
  4. Add two more summary formulas, each with an output type of Number and 2 decimal points.

Capacity

IF(ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__Capacity__c:SUM > 0,
  ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__Capacity__c:SUM, null)

Billable Hours

BLANKVALUE(ResourceHeroApp__Resource_Forecast__c.ResourceHeroApp__RH_Billable__c:SUM, 0)
  1. Add a conditional formatting rule on Billable % for your own target. For an 80% target, end the first range at 60 in red and the second at 80 in yellow, and pick green for everything above.
  2. Click Save & Run.

Things to know

  • Hours follow the checkbox. A time entry counts as billable when Is Billable is checked on it. If a number looks wrong, turn on Detail Rows to see every entry behind it. The Billable and Non-Billable fields are described in The Resource Forecast Object.
  • Time off and holidays arrive on their own. Approved time off and holidays count as non-billable hours automatically. See Time Off Requests and Enhanced Holiday Schedules.
  • Capacity drives the percentage. A resource with no capacity for a month shows an empty cell. See Capacity and Utilization Reporting for how capacity gets created.
  • Report totals cover named resources. Hours on an assignment that has a role but no resource do not belong to any resource row, so the report total can be lower than a sum of every time entry in the org.
  • The same formulas work by role or team. Swap the resource row group and nothing else changes.

Want help setting your billable target? Schedule a call with the Resource Hero team and we will build the reports with you and walk through what they show.